Infinite Construction Development Ltd. v. Chen (Divisional Court)
2023 ONSC 2627 | Ontario Superior Court of Justice — Divisional Court (Corbett J.)
Infinite appealed from the s. 47 ruling that had discharged its lien against our client’s Toronto property. Corbett J. of the Divisional Court dismissed the appeal: the Associate Justice below applied the correct test, made no palpable and overriding error, and was right that Infinite was not a “contractor” under the Construction Act. Costs of $15,000 inclusive payable to our client within 30 days.
The Commercial Problem
The underlying dispute is described in detail at our companion page on Infinite Construction v. Chen, 2022 ONSC 3929. In short: Mr. Chen owned a Toronto property and contracted with 10305391 Canada Inc. (the “Contractor”) for renovation work. Infinite Construction Development Ltd. (“Infinite”) performed substantially all the construction but had no direct contract with Mr. Chen. Infinite registered two claims for lien on title showing $1,185,000 each. On a s. 47 Construction Act motion, Associate Justice Robinson held that the alleged equitable assignment from the Contractor to Infinite failed; that Infinite was not a “contractor” under s. 1(1); and that lien rights had expired before registration. The lien was declared expired, registrations were vacated, and the breach of contract and breach of trust claims were dismissed.
Infinite appealed. Three grounds were raised: (a) Associate Justice Robinson exceeded his jurisdiction by treating a s. 47 motion as a Rule 20 summary judgment motion; (b) on the proper s. 47 test, Infinite had established a “triable issue” that it was a “contractor”; and (c) alternatively, even as a subcontractor, Infinite’s lien was not out of time. The Divisional Court appeal was heard November 30, 2022 by videoconference; reasons were released June 1, 2023.
For a respondent on a Divisional Court appeal from a successful s. 47 motion, the structural risk is that the appeal panel may sympathize with the proportionality concern that animates the threshold debate — that s. 47 should be a narrower exercise than Rule 20 summary judgment — and may be tempted to send some triable issue back for trial. If the appeal succeeds in identifying any issue that ought to have been left for trial, the lien discharge below collapses, the cloud on title returns, and the proceeding restarts. The decisive question on the appeal was whether the multi-pillar reasoning below was structurally sound enough that the loss of any single pillar would not take the result with it.
Strategic Decisions on Appeal
Decision 1: Defend the framework that won below — do not seek expanded relief
The conventional respondent’s temptation on a successful s. 47 appeal is to ask the appellate court to go further: endorse the bad-faith / abuse-of-process argument that did not carry the day below, broaden the doctrinal holdings, expand the costs award. We did not. Asking for more on appeal opens additional fronts on which the appeal panel might disagree, and any disagreement on a peripheral issue gives Infinite a foothold to argue Robinson AJ’s reasoning was over-broad.
We held the line on what we had won. The framework: Maplequest (Vaughan) Developments Inc. v. 2603774 Ontario Inc., 2020 ONSC 4308 (Div Ct) and R&V Construction Management Inc. v. Baradaran, 2020 ONSC 3111 (Div Ct) govern s. 47 motions, with both parties bearing a “best foot forward” obligation. The doctrinal point: “contractor” status is doctrinal, not factual. The disposition: lien discharged, contract and trust claims dismissed, unjust enrichment claim continues as regular Rules action. Each pillar was anchored in the framework Robinson AJ had already applied. Corbett J. accepted the framework substantially as Robinson AJ had set it out (paras. 12–14): “The Associate Justice correctly evaluated the authorities binding upon him on this issue. R&V Construction and Maplequest are panel decisions of the Divisional Court. To the extent that any dicta in GTA General Contractors is inconsistent with these cases, R&V Construction and Maplequest govern.”
Decision 2: Frame the assignment failure as multi-pillar — so any single pillar can fall without taking the result
Robinson AJ’s reasoning on the assignment failure rested on multiple findings: pleadings did not allege assignment; characterizations alternated between “agency”, “representation”, and “assignment”; the Contractor continued to invoice Mr. Chen and receive payments through February 2021 (well after the alleged July 2019 oral assignment); the written “Representation Agreement” was only signed in September 2021, after the liens were registered and after Mr. Chen’s formal demand for the agreement; no notice of the assignment was given to Mr. Chen until September 2021; and no evidence was led from the Contractor’s principal.
Corbett J. agreed with Infinite at para. 16 that one of those findings — the inference from the lack of notice that the Contractor had agreed to assignment — was not as cleanly supported as Robinson AJ had suggested. But the Court of Appeal also held: “Findings (a) to (d) were sufficient to ground the Associate Justice’s decision…. However, this does not mean that there was a triable issue as to whether there was an effective assignment of the contract.” Because we had built the assignment-failure conclusion on multiple independent pillars rather than on a single decisive finding, the loss of one pillar did not take the result with it. The appellate finding that finding (e) was unsupported is captured candidly in our companion page; on this appeal, it cost us nothing.
Honest acknowledgment: this was a partial win on the reasoning below. Corbett J. did agree with Infinite that Robinson AJ’s conclusion on finding (e) was over-stated. Had the assignment-failure analysis rested on finding (e) alone, the appeal would likely have succeeded. The reasoning below survived on appeal because of its multi-pillar structure, not because every pillar was unimpeachable.
Decision 3: Anchor the “contractor” status defence on the doctrinal-not-factual line — Centrum cannot displace the statutory text
Infinite’s alternative argument was that, even without an assignment, its factual role as the entity actually performing all the work and dealing with the owner’s representatives qualified it as a “contractor” under the s. 1(1) Construction Act definition. Infinite leaned on Centrum Renovations & Repair Inc. v. Ditta, 2006 CanLII 39082 (Ont SCJ).
We anchored on the statutory text of s. 1(1): “contractor” means “a person contracting with or employed directly by the owner or an agent of the owner.” The functional indicia of role — running the site, dealing with Mr. Zhang and Mr. Cai, performing all the labour — cannot displace the requirement of a direct contractual relationship with the owner. Corbett J. adopted Robinson AJ’s analysis at paras. 20–21 and quoted directly: “Nothing in the Construction Act prevents a general contractor, who has been contracted by the owner, from subcontracting with a second general contractor to perform the full scope of the first general contractor’s work…. Legally, though, absent a contract with the owner (or an agent of the owner), the second general contractor would still fall within the definition of a ‘subcontractor’ under the Construction Act.” Centrum was distinguished. Infinite was a subcontractor; s. 31(3)(b) applied; the lien was out of time.
Decision 4: Carry the Statute of Frauds and Conveyancing Act alternative arguments forward without making them load-bearing
We had advanced two alternative arguments below that Robinson AJ did not need to decide: (a) that the alleged assignment was void as contrary to s. 4 of the Statute of Frauds (agreements relating to interest in land must be in writing); and (b) that the assignment was ineffective in any event by reason of failure to give notice to Mr. Chen and the operation of s. 53(1) of the Conveyancing and Law of Property Act. We carried both arguments forward into the appeal record as alternative grounds. Corbett J. noted at para. 17: “Both arguments are tenable, but I do not find it necessary to decide them in light of my conclusion that the basis for decision grounding the judgment of the Associate Justice discloses no reversible error.” The arguments served their purpose — alternative grounds available if the primary analysis were rejected — without becoming load-bearing or inviting unfavourable doctrinal precedent.
Outcome
Corbett J.’s decision, dated June 1, 2023, dismissed Infinite’s appeal:
- Appeal dismissed — the lien discharge below stands;
- Lien expired, registrations vacated, and dismissal of the lien-related, breach-of-contract, and breach-of-trust claims all preserved;
- Costs of $15,000 inclusive payable by Infinite to Mr. Chen within 30 days;
- The Associate Justice’s direction that Infinite’s unjust enrichment claim continue as a regular SCJ action (not under the Construction Act) was not appealed and was not disturbed.
If the appeal had been allowed, the consequences for our client would have been substantial: the lien discharge would have been set aside; the $1,185,000 cloud on title would have returned; the breach-of-contract and breach-of-trust claims would have come back into the proceeding; and the entire matter would have proceeded to a Construction Act trial 18–24 months out. By holding the line on the framework and reasoning below — including weathering Corbett J.’s candid disagreement with one specific finding — we preserved the discharge, the title clarity, and the dismissal of the lien-related claims at the appellate level.
Honest qualifier: the appeal was not a complete vindication of the reasoning below. Corbett J. expressly disagreed with Robinson AJ’s treatment of finding (e) on the notice issue, noting that this finding “should have led to a conclusion that there was a triable issue in respect to whether the Contractor had really agreed to an assignment at any point.” The result held because findings (a) through (d) were sufficient on their own. We won the appeal, but the appellate court did not adopt every step of the reasoning below verbatim. The Statute of Frauds and Conveyancing and Law of Property Act s. 53(1) arguments we carried forward as alternative grounds were also not decided, leaving them as available but unestablished doctrine for future cases.
Three Takeaways for Respondents Defending a Successful s. 47 Motion on Appeal
1. Build multi-pillar reasoning at first instance to make the result appeal-resistant. The reasoning below survived on appeal not because every pillar was unimpeachable but because findings (a) through (d) were independently sufficient. When defending a s. 47 motion, do not rely on a single dispositive finding; build the analysis on multiple independent grounds so the loss of any one ground on appeal does not take the result with it.
2. The Maplequest / R&V Construction framework for s. 47 motions is now firmly affirmed at the Divisional Court appellate level. Corbett J. expressly accepted Robinson AJ’s analysis that those panel decisions govern over the dicta in GTA General Contractors, and that proportionality under s. 50(3) of the Construction Act guides the application of s. 47. Practitioners should treat both parties as having a “best foot forward” obligation on s. 47 motions in a manner analogous to Rule 20 summary judgment, subject to the proportionality lens.
3. The contractor / subcontractor distinction in s. 1(1) is doctrinal at the appellate level — Centrum-style functional analysis cannot displace it. The Divisional Court adopted the proposition that absent a direct contract with the owner (or the owner’s agent), no amount of factual indicia of “general contractor role” can establish “contractor” status under the Construction Act. For a subcontractor that has performed all the labour but lacks a direct contract, lien rights expire under s. 31(3)(b) (60 days from last supply), not s. 31(2)(b) (60 days from contract completion).
Are you a respondent defending a successful s. 47 motion on appeal?
On a Divisional Court appeal from a successful s. 47 lien discharge, the structural question is not whether every step of the reasoning below survives the appellate panel’s scrutiny — it is whether the multi-pillar analysis is robust enough that the result holds even if the panel disagrees with one finding. Building that robustness starts at the s. 47 motion record, not at the appeal.
We recommend a 60-minute legal posture assessment before responding to any Divisional Court appeal from a successful s. 47 ruling. We will review the reasons below, the grounds of appeal, the multi-pillar structure of the reasoning, and the realistic risk of partial appellate disagreement on any specific finding. This is a litigation-focused diagnostic, not a sales meeting.
Legal Foundation
This appeal engaged the following framework and authorities:
- Construction Act, R.S.O. 1990, c. C.30 — ss. 1(1) (definitions of “contractor” and “subcontractor”), 31(2)(b) and 31(3)(b) (lien expiry), 47(1), 47(1.1), 47(1.2), 50(3) (procedure of summary character)
- Maplequest (Vaughan) Developments Inc. v. 2603774 Ontario Inc., 2020 ONSC 4308 (Div Ct) — affirmed as governing authority for s. 47 motions
- R&V Construction Management Inc. v. Baradaran, 2020 ONSC 3111 (Div Ct) — affirmed as governing authority for s. 47 motions
- GTA General Contractors Ltd. v. 2566213 Ontario Inc., 2019 ONSC 7370 — dicta inconsistent with Maplequest and R&V Construction not preferred at appellate level
- Centrum Renovations & Repair Inc. v. Ditta, 2006 CanLII 39082 (Ont SCJ) — functional analysis of role distinguished
- Demasi Contracting Inc. and AMT Group Inc., 2013 ONSC 5555 — deficiency remediation does not extend lien rights (affirmed on appeal)
- Statute of Frauds, R.S.O. 1990, c. S.19, s. 4 — alternative argument carried forward on appeal but not decided (Corbett J. at para. 17: “tenable” but not necessary)
- Conveyancing and Law of Property Act, R.S.O. 1990, c. C.34, s. 53(1) — alternative argument carried forward on appeal but not decided
- Divisional Court file: 399/22 — Ontario Superior Court of Justice (Divisional Court); reasons of D.L. Corbett J. dated June 1, 2023; heard November 30, 2022 by videoconference
- Underlying decision: Infinite Construction Development Ltd. v. Chen, 2022 ONSC 3929 (Robinson AJ, June 30, 2022) — the s. 47 lien discharge ruling appealed from
Note on scope: This page describes only the June 1, 2023 Divisional Court appeal disposition. The underlying s. 47 ruling and the surviving unjust enrichment / quantum meruit action are addressed at our companion page on Infinite Construction v. Chen, 2022 ONSC 3929.
This case is publicly reported. All parties are named in the public record. This page summarizes our work for informational purposes only and does not constitute legal advice. Each Divisional Court appeal from a s. 47 motion turns on the multi-pillar structure of the reasoning below, the specific grounds of appeal, the standard of review applicable to each ground, and the alternative grounds preserved in the appeal record. To discuss a specific matter, please contact us.
Related Cases
Infinite Construction v. Chen (Lien Discharge — first instance)
The underlying s. 47 ruling that this appeal affirmed — lien declared expired, $1,185,000 cloud on title vacated, breach-of-contract and breach-of-trust claims dismissed.
Fusion Homes v. Sheikh (Divisional Court Appeal)
Another Divisional Court appellate win — appeal disposed of in the construction-litigation context.
Atlas (Brampton) v. Canada Grace Park (Court of Appeal)
Another appellate win on a multi-theory framework — the panel rejected the principal theory below but affirmed the result on the alternative theory.