Infinite Construction Development Ltd. v. Chen

2022 ONSC 3929 | Ontario Superior Court of Justice (Associate Justice Todd Robinson)

Read the Full Decision on CanLII
Our client owned a Toronto property he had contracted to renovate through a different general contractor. A subcontractor — with no direct contract with our client — registered two claims for lien showing $1,185,000 on title. Associate Justice Robinson discharged the lien on a s. 47 motion: the alleged equitable assignment was unsupported, the claimant was not a “contractor” under the Construction Act, and lien rights had already expired before registration. The breach-of-contract and breach-of-trust claims were also dismissed.

The Commercial Problem

Our client, Yadong Chen, owned a property on Clinton Street in Toronto. In April 2019 he contracted with 10305391 Canada Inc. (“103 Canada”) to renovate the property. Mr. Chen lived outside Canada throughout the project; communications on site went through Mr. Will Zhang and Mr. Clark Cai, his real estate agents from the original purchase. Throughout the two-year project, Mr. Chen continued making payments to 103 Canada by cheque. 103 Canada also continued issuing invoices to Mr. Chen, including one as late as September 24, 2020.

In August and September 2021, the plaintiff Infinite Construction Development Ltd. (“Infinite”), through its principal Mr. Boxuan (Toby) Ma, registered two claims for lien against Mr. Chen’s property. The “Consideration” field on each lien was filled out at $1,185,000. Although the “Statements” portion of the lien forms identified the actual amount claimed at approximately $155,894, the cloud on title that Mr. Chen now had to deal with reflected the much larger figure.

Infinite’s theory was that 103 Canada had orally assigned the renovation contract to Infinite in July 2019, that Infinite had been the de facto general contractor ever since, and that Infinite was therefore entitled to lien rights as a “contractor” under the Construction Act. The written “Representation Agreement” documenting this purported assignment, however, was not signed until September 16, 2021 — three weeks after Infinite had already registered its first claim for lien, and one day before Mr. Chen’s formal email demanding to see the assignment document. When Mr. Ma did show the document to Mr. Chen, the terms and signature date were physically covered with pieces of blank paper.

For a property owner whose property already has a registered lien on title, the structural problem is a binary: until the lien is discharged, the property is encumbered. A bonded vacating motion under the Construction Act requires posting security based on the registered amount — here, potentially $1,185,000 against a claim Infinite was actually pursuing for one-eighth of that. Defending the lien through trial would mean another 18–36 months with title clouded and the owner’s position eroded. The decisive question was whether a s. 47 motion to discharge could establish, on the documentary record alone, that the alleged equitable assignment failed and that Infinite was not a “contractor” under the Construction Act — both of which would defeat the lien at the threshold.

Strategic Decisions

Decision 1: Move under s. 47 of the Construction Act — press the “best foot forward” threshold

The conventional response to a contested lien is to defend through trial: examinations for discovery, motion practice, eventually a multi-day Construction Act trial. That route would have left the $1,185,000 cloud on title for 18–36 months. A s. 47 motion to discharge offered a faster path — if we could demonstrate that there was no triable issue on validity of the assignment or on the lien claimant’s status as a “contractor”.

We pressed Associate Justice Robinson on the threshold. Infinite argued for the more lien-claimant-friendly threshold from GTA General Contractors Ltd. v. 2566213 Ontario Inc., 2019 ONSC 7370 — that a s. 47 motion must fail unless it is “patently obvious” the lien claimant cannot succeed. We anchored on the more rigorous post-Divisional Court framework from R&V Construction Management Inc. v. Baradaran, 2020 ONSC 3111 (Div Ct) and Maplequest (Vaughan) Developments Inc. v. 2603774 Ontario Inc., 2020 ONSC 4308 (Div Ct), under which a s. 47 motion akin to summary judgment imposes a “best foot forward” obligation on both parties. Robinson AJ accepted that framework at paras. 22–23 of the reasons. The threshold debate mattered: it set the evidentiary expectations Infinite had to meet to keep its lien alive, which it ultimately did not meet.

Decision 2: Attack the assignment on three doctrinal pillars — pleadings, Statute of Frauds, and equitable assignment intention

Infinite’s entire claim to lien rights depended on the alleged assignment of the renovation contract from 103 Canada to Infinite. The natural defensive instinct would have been to engage on the factual question of whether Infinite did the work. We did not. Engaging on the factual work-record gives the lien claimant evidentiary footing on the “de facto general contractor” theory.

Instead, we built three doctrinal attacks on the assignment itself. First, the pleadings: Infinite’s statement of claim used “agent and representative” language, not “assignment” language. Robinson AJ accepted at paras. 25–28 that issues are framed by the pleadings (per Rodaro v. Royal Bank of Canada) and that Infinite’s motion position was internally inconsistent with its own statement of claim. Second, the legal-assignment requirements under s. 53(1) of the Conveyancing and Law of Property Act — which Infinite conceded were not met (no written assignment, no notice to debtor before lien registration). Third, the equitable-assignment intention requirement from Nadeau v. Caparelli, 2016 ONCA 730: the form must clearly show an intention that the assignee is to have the benefit of the chose in action. Robinson AJ found at paras. 31–52 that Infinite’s evidence on intention was “sparse”: no affidavit from Mr. Xu (103 Canada’s principal); no contemporaneous documents; no e-signature authentication on the “Representation Agreement”; and Mr. Chen continued paying 103 Canada throughout the alleged assignment period. The equitable-assignment theory failed.

Decision 3: Establish that “contractor” status under the Construction Act is doctrinal, not factual

Even if the assignment had succeeded, Infinite still had to be a “contractor” under s. 1(1) of the Construction Act for the longer 60-day-from-completion lien deadline under s. 31(2)(b) to apply. Infinite argued that its de facto role as general contractor — running site meetings, instructing trades, communicating with Mr. Zhang and Mr. Cai — supported “contractor” status under Centrum Renovations & Repair Inc. v. Ditta, 2006 CanLII 39082.

We pressed the doctrinal point: the Construction Act definitions of “contractor” and “subcontractor” turn on contractual relationships in the construction pyramid, not factual indicia of role. Without a direct contract with the owner (or an agent of the owner), a party performing the full scope of work for a general contractor is still a subcontractor under s. 1(1). Robinson AJ adopted that framework at paras. 57–61. With the assignment failing, Infinite was a subcontractor; s. 31(3)(b) applied (60 days from last supply). We then showed that the only post-July 2021 work was deficiency remediation (which does not extend lien rights under Demasi Contracting Inc. and AMT Group Inc., 2013 ONSC 5555) and pest control (not lienable). The lien rights had expired before either claim for lien was registered.

Decision 4: Frame the $1,185,000 vs $155,894 discrepancy as bad faith / abuse of process — with a candid acknowledgment that the argument was rejected

Each registered claim for lien displayed $1,185,000 in the “Consideration” field on title, while the actual amount Infinite was claiming was $155,894 — a roughly seven-fold discrepancy. We argued under the GTA Restoration framework (where wilful exaggeration of a lien may be a basis for finding abuse of process under s. 47) that the registration was made in bad faith and ought to be discharged on that ground in addition to the assignment and timeliness grounds.

Honest acknowledgment: this argument was rejected. Robinson AJ held at paras. 71–76 that the $1,185,000 figure was a Teraview-generated “Consideration” field error, not part of the prescribed claim-for-lien form, and that the “Statements” section accurately reflected the lien amounts being claimed. He accepted Mr. Ma’s evidence that the higher figure was a misunderstanding about what to put in that field. The discharge order Robinson AJ ultimately granted rested on the assignment and timeliness grounds, not on bad faith. We disclose this candidly because the bad-faith framing is a doctrinally available argument that did not carry the day on this record.

Outcome

Associate Justice Robinson’s decision, dated June 30, 2022, granted Mr. Chen’s motion in part and gave him the operative remedies he had sought:

  • Lien declared expired;
  • Registrations of both claims for lien and the certificate of action vacated — the $1,185,000 cloud on title removed;
  • Action dismissed insofar as the lien remedy is concerned;
  • Breach of contract claim dismissed — no privity of contract between Mr. Chen and Infinite;
  • Breach of trust claim under s. 7(1) of the Construction Act dismissed — Infinite is not a “contractor” and so not a beneficiary of the owner’s trust;
  • Action ordered to continue as a regular action under the Rules, no longer governed by Construction Act procedures.

If we had taken the conventional path of defending the lien through a Construction Act trial, the realistic timeline would have been another 18–36 months: examinations for discovery in late 2022, mediation in 2023, pre-trial in 2023–2024, trial in 2024–2025. During that period, the $1,185,000 cloud on title would have remained, the cost of any refinancing or sale of the property would have been materially higher, and Mr. Chen would have continued to face exposure on lien-related claims that the s. 47 motion ultimately disposed of. Compressing the timeline into a single threshold motion converted a multi-year encumbrance into a single ruling.

Honest qualifier on the residual exposure: two of Infinite’s pleaded causes of action — unjust enrichment and quantum meruit — survived the motion. Robinson AJ held at para. 81 that Mr. Chen had not advanced argument on those claims and so did not meet his onus of demonstrating no triable issue on them. Those claims continue as a regular Rules action. We also sought security for costs under Rules 56.01(1)(d) and (e). Robinson AJ denied that relief at paras. 88–91 because we had elected to rely solely on Infinite’s voluntary financial disclosure rather than conducting independent PPSA, execution, or court-file searches; without that independent evidence, we did not meet the threshold onus. The lien is gone, the contract and trust claims are gone, and the title is clear — but the residual quasi-contractual exposure on the work record continues.

Three Takeaways for Property Owners Facing Inflated Lien Claims from Indirect Contractors

1. The contractor/subcontractor distinction in the Construction Act is doctrinal, not factual. A subcontractor that has performed the entire scope of a general contractor’s work, run the site, and dealt directly with the owner’s representatives is still a subcontractor under s. 1(1) of the Construction Act if there is no direct contract (or valid assignment) with the owner. The 60-day clock under s. 31(3)(b) starts from last supply, not from contract completion. Owners facing inflated subcontractor liens should focus on the contractual chain, not the work-record narrative.

2. Equitable assignment requires more than self-serving assertion. Where the alleged assignment is not in writing, the assignor (here, 103 Canada) must produce evidence of intention — typically an affidavit from the assignor’s principal, contemporaneous documents, or notice to the debtor prior to enforcement. A document e-signed years after the fact, immediately before the assignee’s enforcement step, on the eve of the debtor’s formal demand, with no authentication of the assignor’s signature, will not establish triable issue. Nadeau v. Caparelli, 2016 ONCA 730 sets the standard: the form used must clearly show an intention that the assignee is to have the benefit of the chose in action.

3. If you want security for costs, lead the independent searches yourself. Rule 56.01(1)(d) and (e) place the threshold onus on the moving party. Relying solely on the lien claimant’s voluntary disclosure — financial statements, notices of assessment — is rarely enough. PPSA registrations, writs of seizure and sale, court-file searches, corporate searches: these are the searches that move the threshold from “the lien claimant’s disclosure looks thin” to “there is good reason to believe the lien claimant lacks sufficient assets in Ontario.” Without those searches, the threshold rarely gets met, and the security-for-costs request fails before the just-and-equitable analysis is even reached.

Are you a property owner facing an inflated lien from a party with no direct contract?

When a subcontractor or purported assignee registers a lien against your property — particularly with a “Consideration” figure on title that bears no relation to the underlying claim — the structural question is not whether the work was done. It is whether the lien claimant has the contractual standing to claim a lien at all under the Construction Act, and whether lien rights had already expired before registration.

We recommend a 60-minute legal posture assessment before responding to any registered lien on your property. We will review the contractual chain (owner / general contractor / subcontractor / alleged assignee), the timing of the last supply of services or materials, the “Consideration” vs. “Statements” sections of the registered claims, and the realistic options under s. 47 of the Construction Act. This is a litigation-focused diagnostic, not a sales meeting.

Legal Foundation

This case engaged the following framework and authorities:

  • Construction Act, R.S.O. 1990, c. C.30 — ss. 1(1) (definitions of “contractor” and “subcontractor”), 7(1) (owner’s trust), 31(2)(b) and 31(3)(b) (lien expiry), 47(1), 47(1.1), 47(1.2) (discharge of lien on any proper ground), 50(2), 50(3) (procedure of summary character), 67(2) (court consent for motions in lien actions)
  • Statute of Frauds, R.S.O. 1990, c. S.19, s. 4 — writing requirement for agreements relating to land
  • Conveyancing and Law of Property Act, R.S.O. 1990, c. C.34, s. 53(1) — legal assignment requires writing and notice
  • Personal Property Security Act, R.S.O. 1990, c. P.10 — registration searches relevant to security-for-costs threshold
  • Ontario Rules of Civil Procedure, R.R.O. 1990, Reg. 194 — Rule 5.03(3) (joinder of assignors); Rules 56.01(1)(d) and (e) (security for costs)
  • Maplequest (Vaughan) Developments Inc. v. 2603774 Ontario Inc., 2020 ONSC 4308 (Div Ct) — threshold for s. 47 motion
  • R&V Construction Management Inc. v. Baradaran, 2020 ONSC 3111 (Div Ct) — companion to Maplequest; s. 47 framework
  • GTA Restoration Group Inc. v. Baillie, 2020 ONSC 5190 (Robinson AJ), leave to appeal refused 2021 ONSC 1250 (Div Ct) — “best foot forward” obligation on s. 47 motions; abuse of process by lien exaggeration
  • Hryniak v. Mauldin, 2014 SCC 7 — summary disposition framework analogously applicable to s. 47 motions
  • Nadeau v. Caparelli, 2016 ONCA 730 — equitable assignment intention requirement
  • Yaiguaje v. Chevron Corporation, 2017 ONCA 827 — security for costs holistic approach
  • Demasi Contracting Inc. and AMT Group Inc., 2013 ONSC 5555 — deficiency remediation does not extend lien rights
  • Rodaro v. Royal Bank of Canada (2002), 59 O.R. (3d) 74 (CA) — issues framed by pleadings
  • Court file: CV-21-670068 — Ontario Superior Court of Justice; reasons of Associate Justice Todd Robinson dated June 30, 2022; heard March 2, 2022 by videoconference

Note on scope: This page describes only the June 30, 2022 ruling under s. 47 of the Construction Act. The action continues as a regular Rules action on Infinite’s residual unjust enrichment and quantum meruit claims. Infinite’s appeal from this ruling was dismissed by the Divisional Court — see our companion page on Infinite Construction v. Chen, 2023 ONSC 2627.

This case is publicly reported. All parties are named in the public record. This page summarizes our work for informational purposes only and does not constitute legal advice. Each lien-discharge motion turns on the specific contractual chain, the timing of last supply, the evidentiary record built before the motion, and the doctrinal grounds available under s. 47 of the Construction Act. To discuss a specific matter, please contact us.

Infinite Construction v. Chen, 2022 ONSC 3929: Lien Discharged, $1,185,000 Cloud on Title Vacated | Starkman & Zhang | Starkman & Zhang Lawyers